# | Service/Task | Conditions / Requirements | Timelines | Fees/Remarks | |
---|---|---|---|---|---|
1. | Procurement Process; Specific Procurement Notice | ||||
A. | Solicitation of Advertisement | All bidders in addition to requirements contained in any solicitation documents shall:
| 16 - 24 Days | Minimum of Twenty Thousand Naira only (₦20,000.00) depending on the Complexity and Value of Project. | |
B. | General/Other Public Notices | Minimum 7 days | |||
C. | Bids Opening; Opening of Submitted bids. | Immediately after the close of Submissions | |||
D. | Bid Evaluation/Report Preparation; Preparation of Bid Evaluation and writing of Report. | 14-24 days | |||
E. | Presentation of Report; MTB Consideration and Approval | 14 days | |||
F. | Award and Signing of the Contract; Award | 14 days | |||
2. | Procurement Records Submission: Transmission of Procurement records for the financial year to the Bureau of Public Procurement | 90 days after the end of the financial year. | |||
3. | Response to Complaint on the Outcome of any Procurement Proceedings. | 15 working days. | |||
4. | Response to Bureau Queries/Requests. | Minimum of 10 working days or may be demanded by the Bureau. |